Bidhelp
Ministry of Defence
Department of Defence Production
Not Found
GOA QTY : 105

Items - One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard.,Tools Multimeter,Tools Set of spanners,Tools Allen Key,Tools Cutting Plier,Tools Screw Driver,Binding drawings manuals and documents for installation test and trail,As made drawings manuals and documents for handing over the commissioning,On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE,Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate,Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE,SERVICE ENGINEER CHARGES,TRAINING,One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard.,Tools Multimeter,Tools Set of spanners,Tool

Tender Details
Costs
BOQ
Item NumberItem TitleItem DescriptionItem QuantityUnit of MeasureConsignee IDDelivery Period (In number of days)
1 One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard. INCINERATOR 1 set con4.gsl 90
2 Tools Multimeter INCINERATOR 1 nos con4.gsl 90
3 Tools Set of spanners INCINERATOR 1 nos con4.gsl 90
4 Tools Allen Key INCINERATOR 1 nos con4.gsl 90
5 Tools Cutting Plier INCINERATOR 1 nos con4.gsl 90
6 Tools Screw Driver INCINERATOR 1 nos con4.gsl 90
7 Binding drawings manuals and documents for installation test and trail INCINERATOR 2 set con4.gsl 90
8 As made drawings manuals and documents for handing over the commissioning INCINERATOR 2 set con4.gsl 90
9 On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 90
10 Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate INCINERATOR 1 set con4.gsl 90
11 Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 90
12 SERVICE ENGINEER CHARGES INCINERATOR 1 lum con4.gsl 90
13 TRAINING INCINERATOR 1 lum con4.gsl 90
14 One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard. INCINERATOR 1 set con4.gsl 180
15 Tools Multimeter INCINERATOR 1 nos con4.gsl 180
16 Tools Set of spanners INCINERATOR 1 nos con4.gsl 180
17 Tools Allen Key INCINERATOR 1 nos con4.gsl 180
18 Tools Cutting Plier INCINERATOR 1 nos con4.gsl 180
19 Tools Screw Driver INCINERATOR 1 nos con4.gsl 180
20 Binding drawings manuals and documents for installation test and trail INCINERATOR 2 set con4.gsl 180
21 As made drawings manuals and documents for handing over the commissioning INCINERATOR 2 set con4.gsl 180
22 On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 180
23 Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate INCINERATOR 1 set con4.gsl 180
24 Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 180
25 SERVICE ENGINEER CHARGES INCINERATOR 1 lum con4.gsl 180
26 TRAINING INCINERATOR 1 lum con4.gsl 180
27 One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard. INCINERATOR 1 set con4.gsl 270
28 Tools Multimeter INCINERATOR 1 nos con4.gsl 270
29 Tools Set of spanners INCINERATOR 1 nos con4.gsl 270
30 Tools Allen Key INCINERATOR 1 nos con4.gsl 270
31 Tools Cutting Plier INCINERATOR 1 nos con4.gsl 270
32 Tools Screw Driver INCINERATOR 1 nos con4.gsl 270
33 Binding drawings manuals and documents for installation test and trail INCINERATOR 2 set con4.gsl 270
34 As made drawings manuals and documents for handing over the commissioning INCINERATOR 2 set con4.gsl 270
35 On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 270
36 Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate INCINERATOR 1 set con4.gsl 270
37 Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 270
38 SERVICE ENGINEER CHARGES INCINERATOR 1 lum con4.gsl 270
39 TRAINING INCINERATOR 1 lum con4.gsl 270
40 One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard. INCINERATOR 1 set con4.gsl 360
41 Tools Multimeter INCINERATOR 1 nos con4.gsl 360
42 Tools Set of spanners INCINERATOR 1 nos con4.gsl 360
43 Tools Allen Key INCINERATOR 1 nos con4.gsl 360
44 Tools Cutting Plier INCINERATOR 1 nos con4.gsl 360
45 Tools Screw Driver INCINERATOR 1 nos con4.gsl 360
46 Binding drawings manuals and documents for installation test and trail INCINERATOR 2 set con4.gsl 360
47 As made drawings manuals and documents for handing over the commissioning INCINERATOR 2 set con4.gsl 360
48 On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 360
49 Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate INCINERATOR 1 set con4.gsl 360
50 Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 360
51 SERVICE ENGINEER CHARGES INCINERATOR 1 lum con4.gsl 360
52 TRAINING INCINERATOR 1 lum con4.gsl 360
53 One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard. INCINERATOR 1 set con4.gsl 450
54 Tools Multimeter INCINERATOR 1 nos con4.gsl 450
55 Tools Set of spanners INCINERATOR 1 nos con4.gsl 450
56 Tools Allen Key INCINERATOR 1 nos con4.gsl 450
57 Tools Cutting Plier INCINERATOR 1 nos con4.gsl 450
58 Tools Screw Driver INCINERATOR 1 nos con4.gsl 450
59 Binding drawings manuals and documents for installation test and trail INCINERATOR 2 set con4.gsl 450
60 As made drawings manuals and documents for handing over the commissioning INCINERATOR 2 set con4.gsl 450
61 On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 450
62 Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate INCINERATOR 1 set con4.gsl 450
63 Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 450
64 SERVICE ENGINEER CHARGES INCINERATOR 1 lum con4.gsl 450
65 TRAINING INCINERATOR 1 lum con4.gsl 450
66 One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard. INCINERATOR 1 set con4.gsl 540
67 Tools Multimeter INCINERATOR 1 nos con4.gsl 540
68 Tools Set of spanners INCINERATOR 1 nos con4.gsl 540
69 Tools Allen Key INCINERATOR 1 nos con4.gsl 540
70 Tools Cutting Plier INCINERATOR 1 nos con4.gsl 540
71 Tools Screw Driver INCINERATOR 1 nos con4.gsl 540
72 Binding drawings manuals and documents for installation test and trail INCINERATOR 2 set con4.gsl 540
73 As made drawings manuals and documents for handing over the commissioning INCINERATOR 2 set con4.gsl 540
74 On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 540
75 Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate INCINERATOR 1 set con4.gsl 540
76 Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 540
77 SERVICE ENGINEER CHARGES INCINERATOR 1 lum con4.gsl 540
78 TRAINING INCINERATOR 1 lum con4.gsl 540
79 One complete unit of shipboard incinerator Approx. 180 000 to 200 00 Kcal per hr capacity with all accessories alarms or Instrumentations required for fitment and successful operation onboard. INCINERATOR 1 set con4.gsl 630
80 Tools Multimeter INCINERATOR 1 nos con4.gsl 630
81 Tools Set of spanners INCINERATOR 1 nos con4.gsl 630
82 Tools Allen Key INCINERATOR 1 nos con4.gsl 630
83 Tools Cutting Plier INCINERATOR 1 nos con4.gsl 630
84 Tools Screw Driver INCINERATOR 1 nos con4.gsl 630
85 Binding drawings manuals and documents for installation test and trail INCINERATOR 2 set con4.gsl 630
86 As made drawings manuals and documents for handing over the commissioning INCINERATOR 2 set con4.gsl 630
87 On board spares required for 2 years of maintenance PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 630
88 Inspection and test certificate FAT report duly signed by inspecting authority and report of weighed weight Material test and guarantee certificate INCINERATOR 1 set con4.gsl 630
89 Installation and commissioning spares PRICE BREAK UP TO BE PROVIDED IN PDF FILE INCINERATOR 1 set con4.gsl 630
90 SERVICE ENGINEER CHARGES INCINERATOR 1 lum con4.gsl 630
91 TRAINING INCINERATOR 1 lum con4.gsl 630