Items - Bong USC 1,Bong USC 1,Bong USC 1,Bong USC 1,Bong USC 1,Bong USC 1,Bong USC 2,Bong USC 2,Bong USC 2,Bong USC 2,Bong USC 2,Bong USC 2,Bong USC Visit 1,Bong USC Visit 1,Bong USC Visit 1,Bong USC Visit 1,Bong USC Visit 1,Bong USC Visit 1,Bong USC Visit 2,Bong USC Visit 2,Bong USC Visit 2,Bong USC Visit 2,Bong USC Visit 2,Bong USC Visit 2,Bong Hoist 1,Bong Hoist 1,Bong Hoist 1,Bong Hoist 1,Bong Hoist 1,Bong Hoist 1,Bong Hoist 2,Bong Hoist 2,Bong Hoist 2,Bong Hoist 2,Bong Hoist 2,Bong Hoist 2,Bong Hoist 3,Bong Hoist 3,Bong Hoist 3,Bong Hoist 3,Bong Hoist 3,Bong Hoist 3,Bong Hoist 4,Bong Hoist 4,Bong Hoist 4,Bong Hoist 4,Bong Hoist 4,Bong Hoist 4,Bong Hoist 5,Bong Hoist 5,Bong Hoist 5,Bong Hoist 5,Bong Hoist 5,Bong Hoist 5,Bong Hoist 6,Bong Hoist 6,Bong Hoist 6,Bong Hoist 6,Bong Hoist 6,Bong Hoist 6,Bong Hoist 7,Bong Hoist 7,Bong Hoist 7,Bong Hoist 7,Bong Hoist 7,Bong Hoist 7,Bong Hoist 8,Bong Hoist 8,Bong Hoist 8,Bong Hoist 8,Bong Hoist 8,Bong Hoist 8,Bong Hoist 9,Bong Hoist 9,Bong Hoist 9,Bong Hoist 9,Bong Hoist 9
Item Number | Item Title | Item Description | Item Quantity | Unit of Measure | Consignee ID | Delivery Period (In number of days) |
---|---|---|---|---|---|---|
1 | Bong USC 1 | Supply of USL CRANE 15T LIFT 12.15M LENGTH 19.9M SPAN 9.4 M at Bongaigaon | 3 | Set | esp_purchase1 | 180 |
2 | Bong USC 2 | Supply of USL CRANE 10T LIFT 9.35M LENGTH 15.6M SPAN 7.75 M at Bongaigaon | 3 | Set | esp_purchase1 | 180 |
3 | Bong USC Visit 1 | Visit 1 Supervision for erection of each crane at Bongaigaon Separate visit FOR EACH Crane. | 6 | Set | esp_purchase1 | 180 |
4 | Bong USC Visit 2 | Visit 2 Supervision for PG test of 10T USL crane at Bongaigaon Separate visit FOR EACH Crane. | 6 | Set | esp_purchase1 | 180 |
5 | Bong Hoist 1 | EWR HOIST 2T CAP_LIFT 26.5M LENGTH 15M_MONORAIL ELEVATION AT EL(+)26M FLOOR LEVEL AT EL(-) 0.5 M TRAVEL LENGTH 15M AS PER SPEC FGD EWRH EVO0 FOR LSST A and B TANKS | 2 | Set | esp_purchase1 | 180 |
6 | Bong Hoist 2 | EWR HOIST 2T CAP_ LIFT 21.5M_ LENGTH 20M_ Monorail ELEVATION AT EL(+)21M FLOOR LEVEL AT EL(-)0.5M TRAVEL LENGTH 20M AS PER SPEC FGD EWRH EVO0 FOR AAT TANK | 1 | Set | esp_purchase1 | 180 |
7 | Bong Hoist 3 | EWR HOIST 2T CAP LIFT 18.5M LENGTH 10M. ELECTRIC WIRE ROPE HOIST CAPACITY 2T MONORAIL ELEVATION AT EL(+)18.0M FLOOR LEVEL AT EL(-)0.5M TRAVEL LENGTH 10M AS PER SPEC FGD EWRH REVO0 FOR PHFT TANK. | 1 | Set | esp_purchase1 | 180 |
8 | Bong Hoist 4 | EWR HOIST 3.5T CAP LIFT27.5M LENGTH 19W. ELECTRIC WIRE ROPE HOIST CAPACITY 3.5T MONORAIL ELEVATION AT EL(+)27.0M FLOOR LEVEL AT EL(-)0.5M TRAVEL LENGTH 19M AS PER SPEC FGD EWRH REVO0 FOR SHFT TANK. | 1 | Set | esp_purchase1 | 180 |
9 | Bong Hoist 5 | EWR HOIST 2T CAP LIFT 20.5M LENGTH 13M. ELECTRIC WIRE ROPE HOIST CAPACITY 2T MONORAIL ELEVATION AT EL(+)20.0M FLOOR LEVEL AT EL(-)0.5M TRAVEL LENGTH 13M AS PER SPEC FGD EWRH REVO0 FOR FWT TANK | 1 | Set | esp_purchase1 | 180 |
10 | Bong Hoist 6 | EWR HOIST 2T CAP LIFT 21.5M LENGTH 13M. ELECTRIC WIRE ROPE HOIST CAPACITY 2T MONORAIL ELEVATION AT EL(+)21.0M FLOOR LEVEL AT EL(-)0.5M TRAVEL LENGTH 13M AS PER SPEC FGD EWRH REVO0 FOR WWT TANK. | 1 | Set | esp_purchase1 | 180 |
11 | Bong Hoist 7 | ELECTRIC WIRE ROPE HOIST CAPACITY 2T MONORAIL BEAM ELEVATION. AT EL(+)8.1M FLOOR LEVEL AT EL (+) 0. 0M TRAVEL LENGTH 20M AS PER SPEC FGD EWRH | 3 | Set | esp_purchase1 | 180 |
12 | Bong Hoist 8 | ELECTRIC WIRE ROPE HOIST CAPACITY 2T MONORAIL BEAM ELEVATION AT EL(+)9.32M FLOOR LEVEL AT EL(+)0.0MM TRAVEL LENGTH 20M AS PER SPEC FGD EWRH REV00 FOR RC PUMP OUTLET VALVE. | 3 | Set | esp_purchase1 | 180 |
13 | Bong Hoist 9 | ELECTRIC WIRE ROPE HOIST CAPACITY 2T MONORAIL BEAM ELEVATION AT EL(+)17.37M FLOOR LEVEL AT EL(+)0.0MM TRAVEL LENGTH 15M AS PER SPEC FGD EWRH REV00 FOR ABSORBER AGITATOR. | 3 | Set | esp_purchase1 | 180 |
14 | Bong Hoist 10 | ELECTRIC WIRE ROPE HOIST 2T CAPACITY MONORAIL BEAM ELEVATION EL(+) 18.4M FLOOR LEVEL EL(-) 0.5M TRAVEL LENGHT 20M AS PER SPEC. FGD EWRH REV00 FOR GGH FOR GG TOP BEARING. | 3 | Set | esp_purchase1 | 180 |
15 | Bong Hoist 11 | ELECTRIC WIRE ROPE HOIST 1T CAPACITY MONORAIL BEAM ELEVATION EL(+) 20.0M FLOOR LEVEL EL(-) 0.5M TRAVEL LENGHT 18M AS PER SPEC. FGD EWRH REV00 FOR INLET DUCT BASKET. | 3 | Set | esp_purchase1 | 180 |
16 | Bong Hoist 12 | ELECTRIC WIRE ROPE HOIST 3.5T CAPACITY MONORAIL BEAM ELEVATION EL(+) 18.4M FLOOR LEVEL EL(-) 0.5M TRAVEL LENGHT 15M AS PER SPEC. FGD EWRH REV00 FOR GGH ROTOR RACK & PINION DRIVE. | 3 | Set | esp_purchase1 | 180 |
17 | Bong Hoist visit 1 | Total No of visit for installation where each visit shall be planned separately as one separate visit per hoist | 25 | Set | esp_purchase1 | 180 |
18 | Bong Hoist visit 1 | Total No of visit for PG test - each visit shall be planned separately - one separate visit per hoist | 25 | Set | esp_purchase1 | 180 |
19 | Sipat Hoist 1 | EWR HOIST 20T CAPACITY as per bid - Detail EWR HOIST 20T CAP LIFT 11point7M LENGTH 56M ELECTRIC WIRE ROPE HOIST CAPACITY 20T MONORAIL BEAM ELEVATION AT EL +11.2M FLOOR LEVEL AT EL (-)0.5M TRAVEL LENGTH 56M AS PER SPEC FGD EWRH REVOO FOR BOOSTER FAN MOTOR | 1 | Set | esp_purchase1 | 180 |
20 | Sipat Hoist 2 | EWR HOIST 9T CAP as per bid - DETAIL EWR HOIST 9T CAP LIFT 13.2 M LENGTH 56M.ELECTRIC WIRE ROPE HOIST CAPACITY 9T MONORAIL BEAM ELEVATION AT EL(+)12.7M FLOOR LEVEL AT EL(-0.5M TRAVEL LENGTH 56M AS PER SPEC FGD EWRH REVOO FOR BOOSTER FAN HOUSING. | 1 | Set | esp_purchase1 | 180 |
21 | Sipat visit 1 | First visit for Supervision for installation erection - Separate visit for each hoist | 2 | Set | esp_purchase1 | 180 |
22 | Sipat visit 2 | Second visit for PG Test - Separate visit for each hoist | 2 | Set | esp_purchase1 | 180 |
23 | Korba hoist 1 | ELECTRIC WIRE ROPE HOIST CAPACITY 21.3T MONORAIL BEAM ELEVATION EL (+) 11.25M FLOOR LEVEL EL (+)0.1M TRAVEL LENGTH 51M FOR BUT MOTOR FOR UNIT-1 2 3. | 1 | Set | esp_purchase1 | 180 |
24 | Korba hoist 2 | ELECTRIC WIRE ROPE HOIST CAPACITY 12.3T MONORAIL BEAM ELEVATION EL ( + ) 13.7M FLOOR LEVEL EL ( + )0 . 1M TRAVEL LENGTH 51M FOR BUF FAN HOUSING FOR UNIT-1 2 3. | 1 | Set | esp_purchase1 | 180 |
25 | Korba hoist 3 | ELECTRIC WIRE ROPE HOIST CAPACITY 20.1T MONORAIL BEAM ELEVATION EL ( + ) 10.6M FLOOR LEVEL EL (+)0.1M TRAVEL LENGTH 41M FOR BUF MOTOR FOR UNIT- 4. | 1 | Set | esp_purchase1 | 180 |
26 | Korba hoist 4 | ELECTRIC WIRE ROPE HOIST CAPACITY 13.2T MONORAIL BEAM ELEVATION EL (+) 13.55M FLOOR LEVEL EL (+) 0.1M TRAVEL LENGTH 41M FOR BUF FAN HOUSING FOR UNIT- 4. | 1 | Set | esp_purchase1 | 180 |
27 | Korba hoist 5 | ELECTRIC WIRE ROPE HOIST CAPACITY 20.1T MONORAIL BEAM ELEVATION EL (+) 10.55M FLOOR LEVEL EL (+)0.1M TRAVEL LENGTH 29M FOR BUF MOTOR FOR UNIT- 5. | 1 | Set | esp_purchase1 | 180 |
28 | Korba hoist 6 | ELECTRIC WIRE ROPE HOIST CAPACITY 13.2T MONORAIL BEAM ELEVATION EL (+) 13.6M FLOOR LEVEL EL (+)0.1M TRAVEL LENGTH 29M FOR BUF FAN HOUSING FOR UNIT- 5. | 1 | Set | esp_purchase1 | 180 |
29 | Korba hoist 7 | ELECTRIC WIRE ROPE HOIST CAPACITY 20.1T MONOKAIL BEAM ELEVATION EL () 10.6M FLOOR LEVEL EL (-)0.5M TRAVEL LENGTH 29M FOR BUF MOTOR FOR UNIT- 6. | 1 | Set | esp_purchase1 | 180 |
30 | Korba hoist 8 | ELECTRIC WIRE ROPE HOIST CAPACITY 13.2T MONORAIL BEAM ELEVATION EL (+) 13.55M FLOOR LEVEL EL(-)0.5M TRAVEL LENGTH 29M FOR BUF FAN HOUSING FOR UNIT- 6. | 1 | Set | esp_purchase1 | 180 |
31 | Korba hoist 9 | ELECTRIC WIRE ROPE HOIST CAPACITY 20.1T MONORAIL BEAM ELEVATION EL ( + ) 10. 6M FLOOR LEVEL EL ( + ) 0 . 1.M TRAVEL LENGTH 30m FOR BUF MOTOR FOR UNIT-7. | 1 | Set | esp_purchase1 | 180 |
32 | Korba hoist 10 | ELECTRIC WIRE ROPE HOIST CAPACITY 13.2T MONORAIL BEAM ELEVATION EL ( + ) 15.45M FLOOR LEVEL EL ( + )0.1M TRAVEL LENGTH 30M FOR BUF FAN HOUSING FOR UNIT-7. | 1 | Set | esp_purchase1 | 180 |
33 | Korba visit 1 | SUPERVISION OF ERECTION OF ELECTRIC WIRE ROPE HOIST AS 1ST VISIT AT KORBA PROJECT FOR EACH ELECTRIC HOIST. | 10 | Set | esp_purchase1 | 180 |
34 | Korba visit 2 | SUPERVISION OF ERECTION and PG test OF ELECTRIC WIRE ROPE HOIST AS 2nd VISIT AT KORBA PROJECT FOR EACH ELECTRIC HOIST. | 10 | Set | esp_purchase1 | 180 |
35 | Bhus Hoist 1 | ELECTRIC WIRE ROPE HOIST CAPACITY 5T MONORAIL BEAM ELEVATION AT EL (+) 6. 2M FLOOR LEVEL AT EL (-)1.0M TRAVEL LENGTH 24M VVVFD FOR ALL MOTION AS PER SPEC FGD EWRH REVO0 FOR RC PUMP INLET VALVE. | 1 | Set | esp_purchase1 | 180 |
36 | Bhus Hoist 2 | ELECTRIC WIRE ROPE HOIST CAPACITY 5T MONORAIL BEAM ELEVATION AT EL (+)11.3M FLOOR LEVEL AT EL(- )1.0M TRAVEL LENGTH 24M VVVFD FOR ALL MOTION AS PER SPEC FGD EWRH REVO0 FOR RC PUMP OUTLET VALVE. | 1 | Set | esp_purchase1 | 180 |
37 | Bhus Hoist 3 | ELECTRIC WIRE ROPE HOIST CAPACITY 2T MONORAIL BEAM ELEVATION AT EL (+) 6. 5M FLOOR LEVEL AT EL(-)1.0M TRAVEL LENGTH 6.5M VVVFD FOR ALL MOTION AS PER SPEC FGD EWRH REVO0 FOR ABSORBER AGITATOR. | 2 | Set | esp_purchase1 | 180 |
38 | Bhus Visit 1 | SUPERVISION OF ERECTION OF ELECTRIC WIRE ROPE HOIST AS PER SPEC FGD EWRH REVO0 AT SITE BHUSAWAL PROJECT FIRST VISIT AT SITE FOR EACH HOIST. | 4 | Set | esp_purchase1 | 180 |
39 | Bhus Visit 2 | SUPERVISION OF COMMISSIONING INSPECTION AND TESTING OF ELECTRIC WIRE ROPE HOIST AS PER SPEC FGD EWRH REVOO AT BHUSAWAL FGD SITE AS SECOND VISIT ATSITE FOR EACH HOIST. | 4 | Set | esp_purchase1 | 180 |
40 | Patratu Hoist 1 | ELECTRIC WIRE ROPE HOIST CAPACITY 5T MONORAIL BEAM ELEVATION AT EL (+) 10. 4M FLOOR LEVEL AT EL (-)0.5M TRAVEL LENGTH 35M AS PER SPEC FGD EWRH REVOO FOR RC PUMP INLET VALVE. | 3 | Set | esp_purchase1 | 180 |
41 | Patratu Hoist 2 | ELECTRIC WIRE ROPE HOIST CAPACITY 5T MONORAIL BEAM ELEVATION AT EL (+)15.89M FLOOR LEVEL AT EL(-)0.5M TRAVEL LENGTH 35M AS PER SPEC FGD EWRH REVOO FOR RC PUMP OUTLET VALVE. | 3 | Set | esp_purchase1 | 180 |
42 | Patratu Hoist 3 | ELECTRIC WIRE ROPE HOIST CAPACITY 6T MONORAIL BEAM ELEVATION AT EL(+)18.69M FLOOR LEVEL AT EL (-)0.5M TRAVEL LENGTH 45M AS PER SPEC FGD EWRH REVD() FOR ABSORBER AGITATOR. | 3 | Set | esp_purchase1 | 180 |
43 | Visit Patratu 1 | SUPERVISION OF ERECTION OF ELECTRIC WIRE ROPE HOIST AS PER SPEC FGD EWRH REVCO AT SITE PATRATU PROJECT FIRST VISIT AT SITE FOR EACH 9HOIST. | 9 | Set | esp_purchase1 | 180 |
44 | Visit Patratu 2 | SUPERVISION OF COMMISSIONING INSPECTION AND TESTING OF ELECTRIC WIRE ROPE HOIST AS PER SPEC FGD EWRH REVCO AT PATRATU FGD SITE AS SECOND VISIT ATSITE FOR EACH HOIST. | 9 | Set | esp_purchase1 | 180 |
45 | Mauda Hoist1 | Electric wire rope Hoist capacity 7.5T for vacuum pump | 1 | Set | esp_purchase1 | 150 |
46 | Mauda Hoist 2 | Electric wire rope Hoist capacity 5T for vacuum belt | 1 | Set | esp_purchase1 | 150 |
47 | Mauda visit1 | Sup for install and erection | 2 | Set | esp_purchase1 | 150 |
48 | Mauda visit 2 | Sup for commissioning & PG Test with trial run | 2 | Set | esp_purchase1 | 150 |